Hi friends I guess most of us have compared the option of either constructing a house or buying a ready made apartment. Recently one of my colleague constructed a house in Bangalore and was kind enough to share details with me. I realized that its quite quite painful to accurately estimate the costs.
Contractors predominantly provide cost on the basis of material requirement [material quote] or Area based quote. Area Based quotation is listed on flat per square feet rate. Primarily it is given as ROE (rough order of estimate).
By the way the house was constructed in uttarahalli.
The major problems that you might face is pilferage of resource and work delay. It took my friend nearly 12 months to complete every thing. At the very end discovered that plumbing had some issue and it took about a month to fix.
Contractors predominantly provide cost on the basis of material requirement [material quote] or Area based quote. Area Based quotation is listed on flat per square feet rate. Primarily it is given as ROE (rough order of estimate).
But for material based quotation one provides estimated rates on quantity of material
and estimated total quantity to be used. I learnt from my colleague that using material based quotation we can more accurately access the costs involved. Once we get to know from the contractor the quantity and quality of materials required for the construction, we can analyze the market price for the same. Thus as long as we are aware of the market prevailing price we can keep tab on the overall cost.
With the prevailing rates, for a 1400 sq ft
house costs can start from 19 lakh onwards and go upwards with type of
material chosen for staircase, fittings, flooring and interior. It was primarily ground floor + 1 room and attached bathroom in 1st floor. That is 1200 sq ft in ground floor and 200 in 1st floor.
Let me share with you the breakup :
Borewell,
wiring and motor
|
120000
|
Foundation
(House, compound and car park)
|
200000
|
Ground
floor, staircase
|
250000
|
Water
tank, parapet, compound
|
70000
|
Vitrified
tiles + Ceramic tiles
|
160000
|
Bathroom
Hardware fittings
|
40000
|
Tub, sink
etc
|
70000
|
Electric
wiring
|
160000
|
Plumbing
work
|
120000
|
Miscellaneous
costs, approvals
|
300000
|
Interior
(carpenter and material)
|
300000
|
Approvals
|
120000
|
TOTAL
|
1910000
|
The major problems that you might face is pilferage of resource and work delay. It took my friend nearly 12 months to complete every thing. At the very end discovered that plumbing had some issue and it took about a month to fix.